Water is coming! The Team continues to make significant progress in moving the Phase 2 extension project forward. We have completed the ACT250 public comment period (3/5) and our engineering Team is working to address all comments & feedback.
We have obtained all required easements to allow construction of Phase 2 and the Team is moving quickly into the bid & contract phase. The Phase 2 construction plans are being tweaked and we expect the 100% design to be finalized by the end of March.
Our current schedule is:
1. Design complete (90%) 6/23
2. Permits & approvals: 3/24
3. Request bids (100%): 5/24
4. Evaluate & award: 7/24
5. Begin construction: 9/24
6. Complete construction: 10/25
7. Begin operations: 12/25
Our current focus is on ensuing all potential customers have the ability to sign up early & save $1000.00 off the hook-up fee (Normally $2500.00). It is important that we have the minimum number of committed customers (85) to ensure economic viability. We have hired a part-time project rep / coordinator to assist individuals in understanding what needs to be done & how to process the paperwork. You will enjoy working with Zoe and she can be contacted directly via eMail:
zoe.m.brosky@gmail.com
Our next meeting is Monday, 3/18/24 at 6:30pm in Town Offices.
Anyone interested in clean, safe drinking water in South Alburgh should join!