Construction Work Update Route 2

Past event
Oct 9, 7 AM to 6 PM, Oct 13, 2023

Construction Update
Marshfield-Danville NH PS19(1)
[U.S. Route 2 Resurfacing Project]

TRAFFIC IMPACT AND DURATION: In observance of Indigenous Peoples' Day, crews will be offsite on Monday, October 9.

Tuesday, October 10, through Friday, October 13, between the hours of 7:00 a.m. and 6:00 p.m., motorists can expect lane closures with alternating one-way traffic on U.S. Route 2 (U.S. 2) in Marshfield. Flaggers and Uniform Traffic Officers will be present to assist motorists through the work zone.

CONSTRUCTION ACTIVITIES: Crews will continue cleaning the shoulders of the newly paved roadway beginning near Nasmith Brook Road and progressing east to Bickford's Quarry.
Image of crews paving with cold mix.

LOCATION: Beginning near the Plainfield/Marshfield town line, on U.S. 2, near the intersection of U.S. 2 and Hillside Drive, and extending easterly along U.S. Route 2 to a point just west of the VT Route 15 and U.S. 2 intersection in West Danville.

PROJECTED COMPLETION: Summer 2025
For more information:
Public Information Consultant: Leah Kostick
Project Hotline: 860-815-0269
Email: Leah.Kostick@wsp.com

Back to Calendar

Other Local Events

Northeast Kingdom Community Action at GFPL

Nov 13, 2024, 11 AM to 1 PM

Reading and Writing Club

Nov 14, 2024, 4:30 to 5:30 PM

Bluegrass Show with a Pot Luck Hour

Nov 15, 2024, 7 to 9 PM