TRAFFIC IMPACT AND DURATION: Monday, August 7, through Friday, August 11, between the hours of 6:00 a.m. and 6:00 p.m., motorists can expect lane closures with alternating one-way traffic on U.S. Route 2 (U.S. 2) in Marshfield. Flaggers and Uniform Traffic Officers will be present to assist motorists through the work zone. Motorists are advised to follow the posted speed limit and travel with caution as areas of the roadway are scarified and have a gravel surface with no markings indicating the centerline and edge line.
CONSTRUCTION ACTIVITIES: Crews will continue the second reclamation pass with an emulsion stabilizer, beginning at the Plainfield/Marshfield town line and progressing east for approximately three miles in Marshfield.
Portion of the roadway repaired following the wash outs from the recent flooding events.
LOCATION: Beginning near the Plainfield/Marshfield town line, on U.S. 2, near the intersection of U.S. 2 and Hillside Drive, and extending easterly along U.S. Route 2 to a point just west of the VT Route 15 and U.S. 2 intersection in West Danville.
PROJECTED COMPLETION: Summer 2025
Dec 26, 2024, 7 to 7:45 AM
All Recovery MeetingDec 31, 2024, 10 to 11 AM
New Year's Eve Party at Access Cafe in Montpelier!Dec 31, 2024, 8 PM to 1 AM, Jan 1, 2025