Construction Update May 8-12

Past event
May 8, 6 AM to 6 PM, May 12, 2023

Construction Update
Marshfield-Danville NH PS19(1)
[U.S. Route 2 Resurfacing Project]

DATE: Friday, May 5, 2023

TRAFFIC IMPACT AND DURATION: Monday, May 8, through Friday, May 12, between the hours of 6:00 a.m. and 6:00 p.m., motorists can expect daily lane closures with alternating one-way traffic on U.S. Route 2 (U.S. 2) between Plainfield and Marshfield. Flaggers and Uniformed Traffic Officers will be present to assist motorists through the work zone.

CONSTRUCTION ACTIVITIES: Crews will continue installing erosion control measures and installing underdrain between Plainfield and Marshfield.

LOCATION: Beginning near the Plainfield/Marshfield town line, on U.S. 2, near the intersection of U.S. 2 and Hillside Drive, and extending easterly along U.S. Route 2 to a point just west of the VT Route 15 and U.S. 2 intersection in West Danville.
PROJECTED COMPLETION: Summer 2025

For more information:
Public Information Consultant: Leah Kostick
Project Hotline: 860-815-0269
Email: Leah.Kostick@wsp.com

Back to Calendar

Other Local Events

New Early Time! Life Drawing Studio Nude Model Easels

Dec 31, 2024, 2:30 to 4:30 PM

Arthritis Foundation Exercise Program

Jan 2, 2025, 10 to 11 AM

Indoor Cornhole Games at MSAC

Jan 2, 2025, 2:30 to 4 PM