Town of Bethel, Vermont
State Paving Project Update:
Week of August 19th, 2013
VILLAGE OF BETHEL – (Route 12)
PAVING – Final wearing course paving is tentatively scheduled for Wednesday, 8/21/13 & Thursday, 8/22/13.
Crews will pave in one lane each day as follows:
Wednesday, 8/21/13 – 2:00AM, start paving at the intersection with Route 107 and pave in one lane north to GW Plastics. Paving is expected to extend through the day to mid afternoon.
Thursday, 8/22/13- 2:00AM, crews will again start at the intersection with Route 107 and pave the remaining lane north to GW Plastics. Paving is expected to extend through the day to mid afternoon.
Driveway entrances and side road entrances will be paved in by hand after all of the main roadway paving is complete.
LINE STRIPING – Line striping crews will be working in conjunction with the paving crews. As the paving is occurring, the new line stripes will be placed.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.