Good Morning,
A quick reminder that there will be a public meeting on 10/9, the location has changed from the Library to the Multi-purpose room at BFA. Also, please vote on 10/10.
There have been requests at the previous meetings as well as on social media for a breakdown of the costs of the project. I am working to get these socialized with the community. As always you can contact me with any questions by email at smitchell@fwsu.org or by phone at 309-8974.
Preliminary Project Budget - Prepared by Black River Designs
CONSTRUCTION AND SITE (Hard Costs...)
Construction Estimate (Base) $13,158,612
10% Contingency $1,315,861
Construction Subtotal $14,474,473
Asbestos abatement* $10,000
FEES
A/E Design Fees $1,052,689
Permit Fees
DPS Permit (0.008/$1) $115,796
Act 250 Permit $0
Zoning/Local $0
W/W, Stormwater, Erosion Control $10,000
Clerk of the Works* $150,000
LEED Consultant $0
MEP pre-construction field work $5,000
Lead/Asbestos Consultant/Monitoring* $5,000
Construction Testing Services $10,000
HVAC Commissioning $30,000
Legal Services* $5,000
Surveying* $2,500
Soil Borings* $2,500
Professional Fees Subtotal $1,388,485
MISCELLANEOUS COSTS
Bid Advertising* $500
Printing/Postage/reimbursables* $10,000
Moving/Storage Expenses* $30,000
Interim Financing* $0
Builders Risk Insurance* $10,000
Allowance for above $50,500
OWNER PURCHASES
Furniture* $35,000
Phone System* $0
Equipment (Smartboards, Door access system, AV, Kiln, etc.)* $40,000
Subtotal $75,000
TOTAL PROJECT BUDGET $15,998,458
*Indicates budget items to be finalized/determined by Owner
Cost Breakdown
Sitework
New water main $45,000
At new gym $123,500
At historic entrance $20,975
At new auditorium $39,575
Repave library parking lot $121,360
Courtyard/patio $50,000
stormwater treatment $30,000
New gym addition $2,088,288
Auditorium addition
New area $2,065,070
Existing stage/gym renovation $162,500
MS Gym infill $891,800
Sprinkling $32,000
Multi-purpose & Media Center $272,140
Existing Library $198,950
Cafeteria $152,720
Restrooms
MS $80,000
HS upstairs $80,000
HS downstairs $80,000
Locker Rooms $96,200
Elevator Replacement $109,050
Art $50,800
Music $142,635
HS Science $432,500
Roofing
Existing MS gym $60,000
Reinforce MS gym roof $40,000
Existing Art Room roof $56,250
HS Gym Roof $166,800
Reinforce HS gym roof $22,240
Elementary School MP roof $127,500
MS Science/Art $200,640
Convert HS Art to HS Classrooms $45,976
Health/Nurse $211,140
Sprinkler system
New service $12,000
1972 (HS Gym) building $200,000
Remainder of MS/HS (inc. basement) $344,000
Other renovations
Flooring
Wood floor replacement $246,825
Other $162,860
Ceilings $510,000
Cutting and patching $136,000
Misc doors, accessories, etc. $50,000
Replace 1972 water piping, fittings, etc. $108,000
HVAC
DDC controls $510,000
Heat piping and equipment $411,000
Electrical
LED lighting conversion $699,960
Fire Alarm modifications $10,000
Misc Code violations $10,000
General Conditions $659,500
Mark-up, Insurance, Bonds $792,858
Total: $13,158,612